We are creating projects via Appropriation requests. The theory is that no
commitments should be created before the project is released. However, we have
proven that users can change the Res./Purc. indicator to 'immediate' before the
project has been released. If the approver does not pick up that the project is
not released yet, they can even create a Purchase order.
You can not remove authorisation for the "immediate" indicator, because
the indicator changes when you release the project from "from release" to
"immediate".
How can we stop ANY committments from being created until the project has
been released?
In OPSC make sure the Release immediately has been unmarked.
In transac OPUA (field selection network header) go to influencing choose
network profile or controlling area depending on which you want to customize.
Set the field "Reservation/Purc.req" CAUFVD-AUDISP make it to only displauy.
Go to transac OPUC (field selection network details) go to influencing, choose
network profile or contolling area to which you want to customize the setting.
Set it to change and in the field "Reservation/Purc.req" - AFVGD-AUDISP make it
to only display.
This would prevent the users from changing it to display when they create and
assign activities to networks/projects.
One more customization, in transac OPUU in the network tab make sure the
setting is for 2 (from release)
or
A very effective way to handle this is using User status management .go to
tcode bs02 and define a status profile which can be defaulted in the project
profile, in the status profile define proj definition,WBS,network header and
network activity as the infulenced object types.
Create a status "blck" as an initital status and in the business transaction
field block PR and PRQ creation.
Next create a status"allw" which will be set after project is released and allow
PR and PRQ creation after status is set